Name:     ID: 
 
Email: 

Pre-Architecture Quiz 3

True/False
Indicate whether the statement is true or false.
 

 1. 

To create the Window Schedule for the residential project you will start an existing schedule and modify the fields.
 

 2. 

Room tags are placed before the room is created.
 

 3. 

When placing lights on the ceiling, the symbols shown will also provide light inside the room when the view is rendered.
 

Multiple Choice
Identify the choice that best completes the statement or answers the question.
 

 4. 

To create a new door schedule, you must go to the ______ tool in the ______ panel to begin the process.
a.
Create; View
c.
View; Create
b.
Schedules; Create
d.
Schedules; View
 

 5. 

After creating the door schedule, you will need to add fields to the schedule. Which of the following is not one of the fields used in the door schedule?
a.
Family
c.
Thickness
b.
Head
d.
Count
 

 6. 

When creating a room from two spaces such as the Living Room and Family Room, you must include a _________ line to separate the spaces.
a.
Room Divider
c.
Room Separator
b.
Room Divisor
d.
Room Segmenter
 

 7. 

When calculating the square footage totals for the room finish schedule, the _______ checkbox in the _________ tab must be check first.
a.
Calculate totals; Appearance
c.
Calculate totals; Formatting
b.
Calculate totals; Fields
d.
Calculate area; Filter
 

 8. 

For the Site Plan view, what is the main reason for lowering the bottom of the view range and the view depth to a negative value of -10’-0”?
a.
To see the door and window openings on the floor plan.
c.
To be all to see all of the contour lines of the topography.
b.
To see the ground level of the design.
d.
To be able to see the colors of the materials for the grass and concrete driveway.
 

 9. 

The default material for the topography is _______.
a.
Concrete
c.
Water
b.
Grass
d.
Earth
 

 10. 

What is the name of the tool used to create the concrete driveways and walkways on the surface of the topography?
a.
Subregion
c.
Subsurface
b.
Region
d.
Pad
 

 11. 

When adding stairs to the project the first point is located at the _______ of the stairs.
a.
top
c.
middle
b.
bottom
 

 12. 

In the type properties for the stairs, each step will have a run of ______ inches minimum and a rise of ______ inches maximum.
a.
11; 7
c.
12; 7
b.
11; 5 1/2”
d.
10; 7
 

 13. 

When setting up the roof framing plan view, most of the view is __________ to allow for the elements to be added to be more visible.
a.
hidden
c.
shown in red
b.
darkened
d.
grayed out
 

 14. 

When adding the railings for an existing stair, the ________ tool is used to make sure that the railing will follow the slope of the stairs.
a.
Pick Existing Host
c.
Pick Stair
b.
Pick New Host
d.
Select Old Host
 

 15. 

When creating the interior elevation view of the stairs and railing, what must be done to see the portion of the stairs that located behind the wall?
a.
The graphics for the wall are to be overridden so that it will be placed behind the stairs.
c.
The graphics for the wall are to be overridden so that it will be hidden.
b.
The graphics for the stairs are to be overridden so that it will be transparent.
d.
The graphics for the wall are to be overridden so that it will be transparent.
 

 16. 

The default cut plane setting for a reflected ceiling plan is set to _______ above the associated floor level.
a.
4’-0”
c.
8’-6”
b.
7’-6”
d.
10’-0”
 

 17. 

When placing a ceiling in the project, what are the two methods that may be used?
a.
Pick the walls surrounding the room; Sketch the ceiling outline.
c.
Pick inside the room; Right-click on the room in the project browser and select “Ceiling…”.
b.
Pick inside the room; Sketch the ceiling outline.
d.
Pick the walls surrounding the room; Right-click on the room in the project browser and select “Ceiling…”.
 

 18. 

If you are having trouble placing the ceiling in a room, this may be due to _______.
a.
incorrect ceiling material
c.
incorrect height of the floor
b.
incorrect height of the walls
d.
incorrect thickness of the floor
 

 19. 

What is the name of the tool in the Manage tab, Settings panel that would be selected to remove the 0’ in front of the value for linear dimensions that are less than one foot?
a.
Project Units
c.
Suppress feet display
b.
Calculated
d.
Remove Zero
 

 20. 

When adding a field to the door schedule that is not one of the available fields, you must create your own. To start this process what is the name of the button that you will click first?
a.
Add Parameter…
c.
Add -->
b.
Calculated Value…
d.
Add Field…
 



 
         Start Over